Brownstone scratch coat curing question.
4- 6 weeks is accurate ,Plaster ie sand and cement needs to fully cure .

geoffcapes
in Exteriors 8 years and 8 months ago
2
Please log in, in order to post replies!

homely | 8 years and 8 months ago
string(1) "1" object(WP_User)#4929 (8) { ["data"]=> object(stdClass)#4910 (12) { ["ID"]=> string(6) "178560" ["user_login"]=> string(6) "homely" ["user_pass"]=> string(34) "$P$BhKq7cGwB8jEYvEQE6JJDl2vSEWLhr1" ["user_nicename"]=> string(6) "homely" ["user_email"]=> string(19) "jakarr216@gmail.com" ["user_url"]=> string(21) "/forums/users/homely/" ["user_registered"]=> string(19) "2017-08-10 14:22:45" ["user_activation_key"]=> string(0) "" ["user_status"]=> string(1) "0" ["display_name"]=> string(6) "homely" ["spam"]=> string(1) "0" ["deleted"]=> string(1) "0" } ["ID"]=> int(178560) ["caps"]=> array(2) { ["subscriber"]=> bool(true) ["bbp_participant"]=> bool(true) } ["cap_key"]=> string(15) "wp_capabilities" ["roles"]=> array(2) { [0]=> string(10) "subscriber" [1]=> string(15) "bbp_participant" } ["allcaps"]=> array(4) { ["read"]=> bool(true) ["level_0"]=> bool(true) ["subscriber"]=> bool(true) ["bbp_participant"]=> bool(true) } ["filter"]=> NULL ["site_id":"WP_User":private]=> int(1) }
So I know the final scratch coat should cure for 4 to 6 weeks before the brownstone-colored layer is added. But what if the area is under the stoop and so not in the sun or rain? How long should one wait before applying the final coat?

Augustiner | 8 years and 8 months ago
string(1) "1" object(WP_User)#4931 (8) { ["data"]=> object(stdClass)#4928 (12) { ["ID"]=> string(5) "45573" ["user_login"]=> string(10) "Augustiner" ["user_pass"]=> string(34) "$P$B34SD8yEA6Hi8EPJJfH83mCf4GZmmP0" ["user_nicename"]=> string(10) "augustiner" ["user_email"]=> string(18) "flo@flat-peach.com" ["user_url"]=> string(32) "http:///forums/users/augustiner/" ["user_registered"]=> string(19) "2017-08-10 13:35:10" ["user_activation_key"]=> string(0) "" ["user_status"]=> string(1) "0" ["display_name"]=> string(6) "August" ["spam"]=> string(1) "0" ["deleted"]=> string(1) "0" } ["ID"]=> int(45573) ["caps"]=> array(2) { ["subscriber"]=> bool(true) ["bbp_participant"]=> bool(true) } ["cap_key"]=> string(15) "wp_capabilities" ["roles"]=> array(2) { [0]=> string(10) "subscriber" [1]=> string(15) "bbp_participant" } ["allcaps"]=> array(4) { ["read"]=> bool(true) ["level_0"]=> bool(true) ["subscriber"]=> bool(true) ["bbp_participant"]=> bool(true) } ["filter"]=> NULL ["site_id":"WP_User":private]=> int(1) }
Concrete dries within a couple of days, so I am not so sure if there is really a 4-6 week rule or if the contractors make it up to be able to push your project while working on other sites 🙂 Correct me if I am wrong.