Open Thread


What's Your Take? Leave a Comment

Leave a Reply

  1. Very interesting, chicken, about the costs and the grout.

    Don’t forget the floors. Maybe a day to sand and put down the first coat, then two more days to put down more coats and dry? He was late and in a rush so he put down only one coat as far as I know, then covered the whole thing with paper before it was dry so we could move in the next day.

    I’ve been quoted $2,000 just to do polyurethane, I’ve never heard of anyone installing a whole kitchen for less than $2,000 (but now that I think of it, maybe that included all the materials), and I’ve certainly met a lot of painters who would like to think they should get $2,000 to paint an 800-sf apt.

  2. mopar, that sounds about right by London standards if you’re not paying a middleman although depends how much prep work involved for the painting.

    remove old kitchen – 1/2 day
    install new kitchen – 1 day (add 1/2 day if carcasses need building up)
    tiling and prep – 1 day
    painting prep, undercoat and topcoat – 4 days
    Total = 1 week

    The grouting problem is because he used cheap grout and not enough of it – which is stupid because even the good stuff is fairly cheap and no more difficult to use the right amount.

    He’s chosen the wrong PU sealer or applied it incorrectly – again would not have cost much more to do it right.

    Sounds like he was a general labourer that needed a bit of direction. Day rate of $250 x 7 = $1,750. Add in another day of contingency and you are there. Not good if you are paying taxes on it but not bad for cash in hand.

  3. Here’s a cowboy story for you: My landlady paid $2,000 (labor) for her contractor to install a new kitchen, refinish the floors, and paint my apartment.

    The apartment is probably 800 square feet, and the kitchen is a galley side kitchen but the work involved installing about nine linear feet of cabinets, granite tile counter and backsplash with contrast tile, and a tile floor. Painting included contrast trim.

    Talk about a deal. Half the grout fell out a week later, and six months later the floors have no more polyurethane on them.

    Kitchen still looks pretty good though.

    Isn’t that a crazy price? Poor contractor, he must be more than half way to the poor house by now.

  4. “Lower than 50K?????? Who’s building this? Chickens?

    Posted by: bayridgegirl at April 30, 2009 6:00 PM”

    Well I’m hoping for it to come in sub-$30k (using an exchange rate of 1.5) as we were talking about $40-45k including a second bathroom.

    And that is for some proper guys doing it – it would be closer to $22k if I used a cowboy contractor that I know of.

    I think it’s very interesting to compare the contracting rates between London and NY for what are otherwise fairly comparable-cost cities. I may have to fly these boys over to do the work when I eventually get a house in Brooklyn…

  5. Thanks Chicken. I can’t go this weekend anyway. Still thinking it will be more like the end of the year before I get a place (for lots of reasons).
    I owe you guys dinner (or at least pizza) when you are back.

    Posted by: etson at April 30, 2009 5:57 PM

    You and me both, my friend. Patience is the key…

1 2 3 47