The Atlantic Yards Report writes this morning of two delays relating to the Barclays Center built-out. The biggest news to those who have to try to navigate the giant construction project is that the Carlton Avenue bridge reopening has been delayed by a month, and in order to meet the new completion date of September 2012 work crews will be at it until 3 am. “The artery’s absence could plunge area traffic into chaos, especially given the inevitable shakeout period in which arena-goers and area drivers learn to regulate down their vehicle use before events,” notes AYR. As the blog notes, The $40 million bridge project is an Arena Opening Condition under an agreement Forest City signed with Empire State Development. Delay #2: For the second time in five weeks, says AYR, the “substantial completion date” for the arena itself has been pushed back a week to September 5. (The final completion date is slated for June 30, 2013.)