Inside Third & Bond: Week 85

This week, Hudson talks pavement and mailboxes…
Last week, we received approval for the Third + Bond Builder’s Pavement Plan. Before any of you get ants in your pants: in order to get a new building permit, the BPP must be filed but does not need to be approved.
The BPP is a drawing showing the work to be done to the public realm in conjunction with construction activity on a private lot. The BPP shows sidewalks, curbs and roadway to be reconstructed as well as street trees to keep or be planted. Stormwater catch basins, bus stops, pedestrian ramps, and utility poles are also shown on the BPP.
Often, the BPP is designed by the civil engineer who also does the water and sewer site connection design. It’s logical that these two things go hand-in-hand, since the paving has a direct effect on stormwater run-off and thus the sewer system. Unfortunately, there isn’t a tremendous amount of innovation allowed in either right now. There are a few pilot projects in Queens where DOT is allowing a larger than normal tree pit in order to provide more permeable space to absorb water, but it isn’t a practice that seems easily approved outside of the pilot. So, our BPP is pretty conventional.
Once the BPP is approved, the approved plan is given to the contractor who will pull the permit for the actual work to be done. For example, the approved BPP might require that you will replace ½ of the street width plus 5 feet (common standard), but you can’t actually put a jackhammer to concrete until you have street opening (opening the road bed) and street closing (closing to traffic) permits from the Department of Transportation. Street trees require their own permit from Parks & Rec (Amy Poehler is such a doll!) and sign-off.
Once the work is complete, you call for a field inspection from DOB. You have to pass the field inspection to get your Temporary Certificate of Occupancy. When the paperwork for the BPP catches up, you call for an appointment with the in-office BPP reviewer. His sign-off is necessary in order to get a Permanent Certificate of Occupancy.
We spent as many as four years…
…working toward BPP sign-off before we could get the Permanent Certificate of Occupancy for one of our Roosevelt Island projects. More recently, we’ve had an issue with an affordable housing project of single family houses: the in-office review caught stuck up on freestanding mailboxes. Counterintuitive as it might be, the in-office reviewer is typically more stringent than the field inspector you’d think the guy who can actually measure and look at the physical thing would be the one to not let an unapproved inch sneak by but it’s actually the guy squinting at the photographs you took who has the most questions and objections. In the case of the mailboxes, the in-office reviewer spotted the edge of a mailbox in a photo and wanted to know who owned the box and who put it there. We swore up and down that it was the USPS (who else would put in a group of 16 boxes for 4 houses?) but the reviewer wanted a photograph as proof. So we took a close up of the this box owned by the USPS logo on the back of the box. It was our box, as evidenced by the glimpse of house at the top of the photo, but couldn’t we really have taken that photo of any mailbox in the country with such a logo and given it to the reviewer??
Third + Bond’s mailboxes will be inside the vestibules so that won’t be a hang up this time around. Our other BPP work includes replacing the sidewalk and roadway along our frontage, much of which already shows wear and tear from heavy machinery and trucks passing over it. As for trees, we wanted to put in a street tree for each building, which seemed reasonable given the one tree per 25 feet rule of thumb. However, upon further inspection of existing bus stops, utility and traffic poles, it turned out we could only fit 4 trees. Still, DOT & Parks want us to plant 10 trees and so we’ll end up planting 6 trees off-site at locations that Parks suggests. These trees might easily be placed a block or two away. It’s kind of a bummer not to get the direct benefit of those trees along with the expense, but at least we’re making some more clean air better than being told to repair curb cuts a few blocks away. And even putting in just four trees, we’ll be quadrupling the number of street trees along the frontage of the site compared with when we bought it. Undeniable progress!