November 9, 2006

Electric Slide

IMG_8979.jpg IMG_8981.jpg

Electric progress . . . some switch and outlet action on the Parlor Floor. Also some line for the intercom. Electric is getting there. Plumbing rough is just about done. We are getting estimates for the heating system and will make our choice soon. Thanks for the advice from those who shared!

On the horizon: actually closing up a few walls in the back of the Parlor Floor. The idea is to finish the two back rooms (bedroom and bathroom) ASAP so we can move down there. Then we can finish off the top floor, get it rented and get some income flowing. Then we attack the rest of the bottom two floors. Have I said this before? I think so.

Comments

who the hell is your electrician?

the boxes that are installed are 4" 1900 boxes

your not allowed more than 3 bx cables in any 1 box . From what i can can see there are 6 of them in that box .Boxes packed like that are fire hazard's

Posted by: electricgreek1 at November 9, 2006 11:08 AM

I think it's actually 4 lines into the box, with two just passing behind that look like they go in there too from the picture.

I'm going to speak with my electrician about it though.

Posted by: Peter at November 9, 2006 4:39 PM