Greenwood Heights Backyard: seating area
November 25, 2008
The Final Day Arrives, Phase One Complete!
As the dawn of the last day rose, we were not sure that the crew would be able to finish up with only a half day's worth of "work time" left, but they had surprised us before.
On the hit list: finish up the pavers, bring in the remaining pea gravel, brush in "lock sand" into the pavers and wet it all down so, as Gaspar was fond of saying, "it'll look NICE." (overlay words with a great Canarsie accent)
The remaining pavers went down quickly with most of the more intricate "piece work" taking the bulk of the time, with the crew custom cutting shapes and slices to fit in any remaining gaps in the pattern.

Photo: Making quick work of the paver "piece work."

Photo: Final paver pattern.
Continue reading "The Final Day Arrives, Phase One Complete!"
November 11, 2008
Stone and gravel galore: days five and six.
When last we left off, the patio was poured and faced with cultured stone. We had added back into the mix the 15 foot planter box for the bamboo...the rest of the work would be to finish the install of the remaining cultured stone, add blue stone caps to the box, stairs and patio edge, layout the pathway and seating area, then bring in our reused (and some new) bluestone for stepping stones, layout the pavers on the patio...add in a final layer of pea gravel, then the crew at Your Way Contracting would be done! Here's how the two days went.
The main work yet to be done was the final grading of the yard and the layout of the 11X11 foot seating area and paths.

Photo: Bird's eye view of the work site.
Continue reading "Stone and gravel galore: days five and six."